Journey so far - Validation of Functionality & Technology
Alta Wave 1000H Timeline

STAGE 1 (TRL 1-3)
2016 - 2017- 2018
Concept Validation
Prototype NoviOcean No1 Scale 1:7
COMPLETED

STAGE 2 (TRL 4-5)
2019 - 2020- 2021
1:6 Scale Prototype
0.9 M€
COMPLETED

STAGE 3 (TRL 6)
2022 - 2023- 2024
1:5 Scale Prototype
2 M€
COMPLETED

STAGE 4 (TRL 7)
2025 - 2026- 2027
1:1 Scale Pilot Project
4 M€

STAGE 5 (TRL 8)
2028 - 2029- 2030
Pre-commercial Array

COMMERCIAL (TRL 9)
2031 - 2032
Commercial Deployment
Medi Wave 800H Timeline

STAGE 4 (TRL 7)
2025-2026
1:1 Scale Pilot Project
Project Costs
5 M€

STAGE 5 (TRL 8)
2027-2028
Pre-commercial Array
Project Costs
5 M€

STAGE 6 COMMERCIAL (TRL 9)
2029 =>
Commercial Deployment
Project Costs
5 M€
Key highlights –
NoviOcean adheres to a globally recognized Product Build, Test, and Commercial Deployment Methodology (TRL)
Prototype connected to a local grid powering a small island
24 Months in Test Rig at Royal School of Technology (KTH)
6 Weeks of Wave Tank Testing (UK and France)
18 Months testing in Actual Offshore Conditions
Third Party Simulations validates the performance
Triple Patents secured for 20 relevant markets**
Design of Full-Scale Unit well underway