A NoviOcean hybrid wave, wind and solar platform moored offshore in front of a large coastal data center facility

Featured application

Coastal data centers and critical infrastructure

Generation in the water in front of the load — wave, wind and solar on one structure, added a unit at a time as the campus grows.

For illustration only — the actual design is shared in closer dialogues.

Featured application 02

One of four priority early applications for the NoviOcean platform. This page sets out the customer problem, what NoviOcean brings to it, the evidence a buyer of firm supply actually needs, and a possible route to a first project.

Try it

What would an array do for your campus?

Set the array size and the campus load. The model returns the share of that load a NoviOcean array could cover in a representative year. It is a supply calculation, not a resilience one — see the note under the results.

140
10200
80300
Demand covered % of the annual demand set above
Rated capacity MW array nameplate, 850 kW per unit
Emissions avoided t CO₂e/yr at ~1 tonne per MWh delivered
Indicative cost gap €/yr delivered energy at the reference price, less the same energy at ~7 c€/kWh
Share of the demand set above

This models supply only. It does not replace UPS, N+1 backup or any continuity guarantee, and NoviOcean does not claim it does. Sites with strict continuity requirements pair the platform with existing backup rather than substituting for it.

Illustrative scenario based on representative assumptions. Actual performance depends on location, wave climate, wind, solar irradiation, configuration, load profile and local energy costs. Contact NoviOcean for a site-specific assessment.

The assumptions behind these numbers
AssumptionValueSource
Rated power per unit850 kW — 300 wave / 350 wind / 200 solarDeck slide 6; identical on Technology, Medi Wave 850H, Validation and Simulator modeled
Annual production per unit~2,500 MWh per yearDeck slide 22 — representative modeled production, not guaranteed for your site modeled
Diesel displaced400 litres per MWh deliveredDerived from ~1,000,000 litres per 2,500 MWh, deck slide 22 modeled
Emissions avoided~1 tonne CO₂e per MWh deliveredDerived from ~2,500 t per 2,500 MWh, deck slide 22 modeled
NoviOcean energy cost~70 €/MWh (~7 c€/kWh)Conservative end of the Stage A range, 4–8 c€/kWh, deck slide 26 projected
Capacity factornot usedV2 publishes no Medi Wave capacity factor. Annual energy comes straight from the published figure above, never from a capacity factor. estimate

Demand and price above are illustrative defaults, not your site’s figures, and no local wave, wind, solar or demand data has been used. Output is representative modeled production, not a guarantee.

The customer problem

Rapidly growing electricity demand, and interest in local, more stable clean energy.

Data centers and other critical coastal infrastructure are not short of megawatt-hours in the abstract. They are short of megawatt-hours at a particular place, on a particular date, with a clean and verifiable origin — and that is a harder thing to buy than it used to be.

Demand outruns the connection

Load growth is arriving faster than onshore grid connections are being built. A campus can be financed, designed, permitted and staffed long before the connection that feeds it is energised, and the schedule that matters to the operator is rarely the schedule the network can commit to.

The coast is a constrained edge

Coastal sites are chosen for cable landings, cooling water and latency — which puts them at the edge of the transmission network rather than at its centre. Queue times and constrained coastal substations are a real constraint, and reinforcement takes years that sit outside the operator’s control.

Local and additional, not certificates

Operators increasingly want generation that is local, additional and demonstrably clean — power that can be pointed at from the site, rather than certificates bought at a distance and matched on an annual balance. Proximity is becoming part of the definition of clean supply.

  • NoviOcean publishes no figure for global or regional data-center electricity demand. Where a number would help the argument and no verified source exists, the sentence is written without one.
  • Whether an offshore hybrid unit is the right answer at a given site depends on the wave climate, wind, irradiation, water depth, seabed, distance to the campus and the local cost of energy. Those are assessment questions, not marketing ones.
NoviOcean Medi Wave 850H hybrid platform at sea, the yellow wave floats, solar deck and vertical-axis wind turbines that make up one 850 kW unit

What NoviOcean brings

Put the generation in front of the load.

Generation at the water’s edge

The platform is moored offshore from the site, so generation sits in the water in front of the load rather than at the far end of a congested onshore connection. Nothing competes for land beside the campus, and the power reaches it over a short route the project controls.

One structure, three sources, whole units

Wave, wind and solar are collected on one structure, with one mooring, one cable and one installation — so a campus adds capacity in whole units instead of commissioning three separate offshore projects, each with its own consent, vessel campaign and connection.

Each unit is rated at 850 kW: 300 kW wave, 350 kW wind and 200 kW solar. management estimate The design is intended to scale from single units to offshore arrays of up to 5 MW. management estimate

More hours, not only more megawatt-hours

Wave, wind and solar are off-phased: waves continue long after the wind that raised them has dropped, and rebuild as new wind systems form. Because the three sources rarely peak together, a hybrid unit delivers across more hours of the day and the year than a single-source plant of the same rating. modeled

For a load that runs continuously, hours of supply matter more than headline capacity — which is why the comparison below is drawn at system level rather than at generator level.

See the baseload evidence behind the off-phasing

The evidence that matters here

Cheap generation alone is insufficient — the full energy system is what matters.

A buyer of firm supply is not buying a generator, but a system that keeps a load steady. Once the storage, backup and oversizing needed to serve that load are counted, the ranking by headline cost of energy is not the ranking that survives.

What it takes to serve a reliable 10 MW load modeled
Storage & backup need Total system CAPEX Lower is better Low Low–moderate Moderate Moderate–high High Very high Solar only Wind only Wind + solar NoviOcean hybrid very high storage high storage moderate storage low–moderate storage Qualitative system ratings from NoviOcean’s own system modelling — relative, not absolute.

The same comparison, in full

Comparison of solar only, wind only, wind plus solar and the NoviOcean hybrid across generation cost, standalone cost of energy, storage and backup need, installed capacity for a reliable 10 MW load, total system cost and round-the-clock economics.
System Generation CAPEX / MW Standalone LCOE Storage & backup need Installed capacity for a reliable 10 MW load Total system CAPEX Reliable 24/7 economics
Solar only Low Very low Very high Very high Very high Weak
Wind only Moderate Low High High High Moderate
Wind + solar Low–moderate Low Moderate Moderate–high Moderate–high Moderate
NoviOcean hybrid Moderate Competitive Low–moderate Moderate Moderate Strong

Qualitative system comparison from NoviOcean’s own system modelling (Extended Presentation, slide 9). Ratings are relative, not absolute, and depend on the site, the load profile and local energy prices. The 10 MW load is an illustrative reference case, not a quotation for any particular campus.

Per unit

What a campus actually gets.

Three figures, each with the evidence behind it. Annual production is representative modelled output, not a guarantee for any particular location.

850 kW

Rated power, per unit

300 kW wave, 350 kW wind and 200 kW solar, from one structure, one mooring and one cable to shore.

management estimate

~2,500 MWh

Per unit, per year

Representative modelled production. Actual output depends on the wave climate, wind, irradiation and configuration at the site.

modeled

Up to 5 MW

Array scale

The design is intended to scale from a single unit to offshore arrays, so a campus can expand in step with its own load growth.

management estimate

Want these figures for a specific array size and load? The scenario tool builds an illustrative case with every assumption visible on screen.

Try the scenario simulator

A possible project pathway

Start with an assessment, not an order.

A generic route, written to be understood before a first conversation. It names no customer, country or partner, and describes no committed project.

Step 01 — Load and site assessment

A joint review with the operator: the campus load profile and its growth plan, the connection position and its constraints, and the wave, wind and irradiation conditions at the candidate sea area, together with depth, seabed and distance to shore.

Step 02 — A first co-located unit

One unit sited in front of the campus under a power-purchase or lease arrangement, so the operator buys energy or capacity rather than a prototype. Ownership can sit with the operator, with a project company, or with a partner that runs the plant and sells the output.

Step 03 — Staged expansion

Further units added in step with the campus, each one a repeat of a configuration that has already been built and operated at that site — expansion by replication rather than by a new offshore programme each time.

What a NoviOcean unit is for

  • Local, additional generation sited in front of the load
  • Wave, wind and solar capacity added in whole 850 kW units management estimate
  • Production spread across more hours than a single-source plant of the same rating modeled
  • Staged expansion in step with campus load growth
  • Pairing with onshore storage where continuity requirements are strict

What it does not claim to be

  • Not a replacement for uninterruptible power supply (UPS)
  • Not a replacement for N+1 or other on-site backup generation
  • Not a substitute for the grid connection or for a site’s contracted supply
  • Not a guaranteed output figure for any particular location
  • Not a claim that every coastal campus is a suitable site

Sites with strict continuity requirements pair the platform with onshore storage rather than replacing existing backup. NoviOcean supplies clean, local energy into the campus; the resilience architecture — UPS, backup generation, redundancy — stays exactly where the operator’s standards already put it.

Related applications

The same platform, sited for a different job.

Coastal campuses are one of approximately twelve credible applications. management estimate These three are the nearest neighbours to a data-center project.

Bring the generation to the campus.

Tell us the site, the load profile and what the connection currently allows. We will tell you honestly whether an offshore hybrid unit is a sensible fit for it — and what an assessment would involve.